Pleasant Street Construction Update 5/19/2017

Pleasant Street Reconstruction Project - May 19, 2017

 

As of Thursday May 18, 2017 the following work has occurred:

  • Repaired and lined the existing sewer.
  • Verizon installed new utility poles between Main Street and Cambridge Street.
  • Installed new 8-inch water main and services from Main Street to Groton Street.
  • Installed new drainage structures and pipe from Main Street to Groton Street.
  • National Grid installed a new gas main and services between Main Street and Groton Street.
  • Removed existing sidewalk and curbing.
  • Installed binder course pavement, asphalt berm, and adjusted castings.
  • Granite curbing is being installed.
  • Sidewalks are being prepared for pouring.

The following work is anticipated on Saturday, May 20th:

  • Please be advised that General Contractor Ricciardi Bros., Inc., will be adjusting remaining drainage castings on Pleasant Street this Saturday.

NO on-street parking will be allowed during construction. Local access will be allowed. Detours will be setup as necessary and detail officers will be onsite to direct traffic.

The Ayer DPW appreciates your cooperation during this important project. If you have any questions, please call the Ayer DPW at 978-772-8240 (7:30 to 3:30) or email DPW@ayer.ma.us