High Street Paving & Sidewalks Begins Friday, September 17
Posted on: September 16, 2021 - 11:34am
The Ayer DPW will be paving High Street from Holmes Street to Winthrop Avenue beginning on Friday September 17th. The work includes new asphalt sidewalks and curb and repaving the street.
Work sequence will be:
- Remove existing sidewalks
- Remove existing pavement and regrade (Reclaim)
- Install binder course pavement
- Install curbing
- Construct sidewalks and ramps
- Final paving
The project is anticipated to take several weeks.
Seek alternative routes. Police details will be onsite to direct traffic.
During construction, there will be varying road conditions. Please travel with caution.
If you have any questions, please contact the Department of Public Works at 978-772-8240.