Construction Update - East Main Street Reconstruction Project

April 26, 2022

The East Main Street Road Reconstruction Project is nearing completion. The following work is anticipated in the coming weeks:

Remainder of this week (April 25th-29th):
The Contractor will be adjusting manholes and catch basin grates to proper elevation for final grade.

Week of May 2nd:
The Contractor will conduct pavement milling of the side streets connecting to East Main Street. Approximately 50-feet of each side street will be milled from East Main Street.

Week of May 9th: 
The Contractor will perform final paving. Additional notices will be distributed prior to final paving to indicate any traffic detours required.

After paving there will be signage, pavement markings, and other finishing work.

Please travel with caution during construction.

This project is being managed by MassDOT and the Ayer DPW is providing construction updates to provide work status and traffic impacts.

If you have any questions, please contact the Department of Public Works at 978-772-8240.