Pleasant Street Construction Update 6/22/2017

Pleasant Street Reconstruction Project June 22, 2017

As of Wednesday June 21, 2017 the following work has occurred:

  • Repaired and lined the existing sewer.
  • Verizon installed new utility poles between Main Street and Cambridge Street.
  • Installed new 8-inch water main and services from Main Street to Groton Street.
  • Installed new drainage structures and pipe from Main Street to Groton Street.
  • National Grid installed a new gas main and services between Main Street and Groton Street.
  • Removed existing sidewalk and curbing.
  • Installed binder course pavement, asphalt berm, and adjusted castings.
  • Installed granite curbing, concrete sidewalks, ramps, and aprons.

The following work is anticipated starting Thursday June 22, 2017:

  • Top course paving has been rescheduled for Monday June 26th (weather permitting).
  • The Contractor will also be installing signage, striping the roadway, and completing sidewalk tie-ins.

NO on-street parking will be allowed during construction. Local access will be allowed. Detours will be setup as necessary and detail officers will be onsite to direct traffic.

The Ayer DPW appreciates your cooperation during this important project. If you have any questions, please call the Ayer DPW at 978-772-8240 (7:30 to 3:30) or email DPW@ayer.ma.us