Spectacle Pond Transmission Main Replacement Project

Bid Number: 
23DPW02
Start / End Dates & Times: 
08/12/2022 - 2:30pm to 09/14/2022 - 2:00pm
Bid: Closed

SUBSCRIBE TO UPDATES BELOW TO OBTAIN BID DOCUMENTS AND BE NOTIFIED OF FUTURE ADDENDA

Sealed Bids for the construction of the “Spectacle Pond Transmission Main Replacement Project” will be received by the Ayer Department of Public Works Office, 25 Brook Street, Ayer, MA 01432 until 2:00 p.m. local time on September 14th, 2022 at which time the Bids received will be publicly opened and read.  Sealed Bids must have outer envelope marked as “Spectacle Pond Transmission Main Replacement Project”.

The work consists of the installation of approximately 750 linear feet of 18-inch high density polyethylene (HDPE) transmission main at the Spectacle Pond Water Treatment Plant (WTP). The work includes new water main appurtenances, reconnections to existing mains, and includes installing a portion of the main underneath a 48-inch culvert within the limits of work. Bids shall be on a unit price basis as indicated in the Bid Form.

All Bids for this project are subject to the provisions of Massachusetts General Laws Chapter 30, Section 39M as amended.

A bid deposit shall be furnished in accordance with the Instructions to Bidders.

This Contract contains price adjustments for diesel fuel and gasoline.  See Section 01270 for payment procedures and base prices for this Project.

Minimum Wage Rates as determined by the Commissioner of Department of Workforce Development under the provision of the Massachusetts General Laws, Chapter 149, Section 26 to 27D, as amended, apply to this project. 

Subscribe to Updates

The form below must be filled out, as this will ensure you automatically receive any associated addendums. Once completed, you will then be able to view the Bid/RFP.

Business Information

By clicking submit, you are acknowledging that you will receive an email notification with a link back to the website whenever an addendum is posted to this bid.